Ceredigion County Council’s Active Travel Network Map Milestones

Over the course of 2020 and 2021, local residents, organisations and businesses have the opportunity to help shape and influence the future network of Active Travel routes in Ceredigion by getting involved in the Active Travel Network Map preparation process, as set out below.
  • Integrated Network Maps approved by Welsh Government

    November 2017

     

    -

     

    January 2018

    Ceredigion Integrated Network Maps (INM) approved by Welsh Government.
  • 2017 INM’s due for revision

    September 2020

     

    -

     

    September 2020

    INMs are to be revised every 3 years. Due to Covid-19 the deadline was extended to December 2021.
  • Active Travel Network Map (ATNM) consultation – Phase 1

    November 2020

     

    -

     

    January 2021

    Gather information from the public on barriers to cycling and walking in Ceredigion.
  • Active Travel Network Map consultation – Phase 2

    March 2021

     

    -

     

    March 2021

    Gather thoughts relating to the refined ATNM proposals.
  • Active Travel Network Map Statutory Consultation

    27 August 2021

     

    -

     

    19 November 2021

    Full public consultation on the revised draft network prior to submission to Welsh Government for approval.
  • Active Travel Network Maps to be submitted to Welsh Government for approval

    31 December 2021

     

    -

     

    31 December 2021

    Revised ATNMs to be submitted for approval to Welsh Government.